Mesa Morenos 76 MW- Wind Project in Mexico


Icono localizaciónMESA MORENOS

Icono título76 MW WIND PROJECT IN MEXICO

Technology: Wind

Power: 76 MW

Market: MEXICO

Construction: 2018 Q1

Start of operation: 2019 Q2


Project Details

BAS CORPORATION owns the “Mesa Morenos” project developed by EOLIATEC (Exclusive Purchasing Agreement, conditioned to favorable Due Diligence).

The site is located in the Municipality of Pinos, Jalisco, 33 km from the municipal head.

Wind measurements performed by the developers with an anemometric tower 50 m in height from jan 2012 to date and with an anemometric tower 80 m in height from march 2015 to date.

The estimated production is 268.6 GWh/year (P50) corresponding to a plant factor of approximately 40.4%.

Connection Node: Aguascalientes Oriente.

The Project is a self-supply power plant that has bilateral PPAs for a tranche of its energy and another merchant tranche.

ENERGY: All permits obtained: Energy Self-Storage Permit (CRE), Indicative study (CENACE), System Impact Study (CENACE), Facilities Study (CENACE), Facilities and Assignment Agreement (CENACE), Interconnection Contract (CFE). CENACE (https://www.gob.mx/cenace).